Malaysia Offshore Oil Platform Protection
2026-04-02
Offshore Oil Platform Protection, Malaysia
Location : Malaysia
Asset : Offshore oil platform
Year : 2007
Application : Primary containment and abrasion protection
Scope : Protection for upper decks and internal structures
Coating System : ST coating, 1 mm thickness
Coated Area : 440 m²
Key Challenges
- Extremely tight construction schedule with only a few days allowed for recoating.
- Slow-curing products could not be used due to limited turnaround time.
- Closed and confined working spaces requiring low or zero VOC materials for safety.
- Heavy offshore exposure demanding strong abrasion and mechanical resistance.
Solutions & Execution
- Substrates were blast cleaned to a surface profile of 50–80 microns in accordance with industry standards.
- ST coating was applied at a thickness of 1 mm across all treated areas.
- Featuring rapid curing and excellent physical performance, ST perfectly fit the compressed timeline.
- Zero VOC formulation ensured safe application inside confined offshore compartments.
- The lining was ready for inspection and testing within 3 hours, and the assets were fully returned to service within 4 hours.
![latest company case about [#aname#]](http://style.spraypipelining.com/images/lazy_load.png)
![latest company case about [#aname#]](http://style.spraypipelining.com/images/lazy_load.png)
![latest company case about [#aname#]](http://style.spraypipelining.com/images/lazy_load.png)
![latest company case about [#aname#]](http://style.spraypipelining.com/images/lazy_load.png)