Latest company case about Beijing Sewage DN1600 Small Manhole Cement Pipeline Rehabilitaion

Beijing Sewage DN1600 Small Manhole Cement Pipeline Rehabilitaion

2026-05-22

Beijing Sewage DN1600 Small Manhole Cement Pipeline Rehabilitaion


Project Location: Shunyi District, Beijing

Pipeline Specification: DN1600 concrete pipeline

Manhole Condition: Non-standard small-sized manhole chamber with a manhole opening of only 680mm, narrower than conventional standard size

Burial Depth: Pipeline burial depth exceeds 5 meters

latest company case about Beijing Sewage DN1600 Small Manhole Cement Pipeline Rehabilitaion

Key Challenges:
  • Limited construction space caused by small non-standard manhole (680mm opening) matching large-diameter (DN1600) pipeline
  • Difficult working conditions due to ultra-deep pipeline burial depth of over 5 meters
  • Tight and urgent project schedule requiring temporary on-site adjustment of the original repair process